Initial situation  

In recent years, the number of passengers on the Zentralbahn has risen steadily – with the exception of 2020 – which means that the Zentralbahn will need more rolling stock in the future. A storage concept for 2021 to 2050 also determined the space required for this rolling stock on the north side of Brünig. There is currently a shortfall of around 2.6 km of storage length. In order to be able to store additional vehicles in Giswil in the future, the storage facility must be expanded by two new tracks.   

All railway engineering requirements can be met to the east of Giswil station, provided that the facility is protected by a gallery.

Objective of the construction project  

  • Creation of new tracks for storing rolling stock. 
  • Increased safety against natural hazards. 
  • Expansion and upgrading of existing cable systems. 
  • Expansion of signaling systems in Giswil.

Construction schedule and work  

Preliminary work: End of October 2024  

  • Start of construction on October 28, 2024 
  • Safety felling and rock clearing 
  • Setting up installation sites 
  • Clearing Adding pipe systems (night work) 
  • Conversion of catenary systems (night work)  

Main work: January to December 2025  

  • Excavation work 
  • Excavation pit safety measures 
  • Foundation work 
  • Concrete construction 
  • Adding pipe systems (night work) 
  • Adjusting track systems (night work) 
  • Conversion of catenary systems (night work)  

Follow-up work: spring 2026  

  • Reforestation and planting 
  • Dismantling of installation sites